Some pieces are too heavy, too high or too far in for a lift truck. Those go on a brought-in crane: the crane and its operator are hired for the job, and our crew plans the lift, rigs the load and runs the day. Every pick gets a written plan, a cleared zone and one signaller.
The lift plan
Every lift is a critical lift
The pick is worked out on paper before the crane shows up. If there is a number we don't know, we find it before the day. Nobody estimates it with the load in the air.



The load
Weight, rigging, centre of gravity
We start with the nameplate weight and add whatever is still bolted on. The lifting points get checked. Slings and shackles are rated for the load at the angle the slings will hang, because a flatter sling works harder. Where a piece can't take a sideways pull, a spreader beam goes on to hold the slings apart.
The crane
Radius and chart
A crane lifts less the farther out it reaches. So it is sized for the worst point of the lift, which is usually the set-down at the longest radius. The capacity chart is read for the way the crane is actually set up, and the hook block and rigging count as part of the load.
The ground
Outriggers and mats
Outriggers are the legs a crane puts out to stand on. We check what is under each pad: paving, gravel, frost, buried services, basements and vaults. Mats and cribbing, which is stacked timber blocking, go down to spread the weight.



Rooftop work
Cooling towers, rooftop units and chillers



A lot of our crane work happens on roofs. Cooling towers, air-handling and condensing units, chillers and exhaust equipment come off a curb, the raised frame a unit sits on, well back from the roof edge, and get set on a trailer below. The plan covers the parapet, the roof structure under the path the load travels and the people on the ground.
If the unit is being replaced, the new one goes up in the same window the old one comes down. The crane comes to site once, and your building goes without cooling for the shortest time the job allows.
Heavy machinery and tight sites
Through the roof, over the wall, into the pit
When a press brake or a machining centre can't be walked out the door, it leaves through a roof opening or over a wall. A process skid gets landed in a pit or up on elevated steel. These are tight lifts on sites that are still working, often with the crane set up on a street or a loading dock.
The swing path is laid out to keep the load away from occupied areas. Tag lines, the ropes a rigger uses to steer a hanging piece, keep hands at a safe distance. Where the crane can't reach the set point, it lands the piece at the door, and our lift trucks and rigging crew take it the rest of the way.
On the day
One signaller and a cleared zone
The crew
The crane operator, our riggers and one signaller all work to our lift plan. Before anything leaves the ground, a pre-lift meeting walks through it with the whole crew and the building's people.
Exclusion zone
The ground under the load path and around the crane is barricaded, and it stays clear for the whole lift. Nobody walks under a suspended load, however quick the shortcut looks.
One voice
One signaller directs the operator, so the operator only ever hears one voice. Wind, visibility and ground are checked that morning. If the day is wrong, the lift waits.
How it fits
Crane, lift truck or both
Most machinery moves never need a crane. Our lift trucks do the work inside the building, and the crane takes the heavy, the high and the roof. On a plant deconstruction the two run side by side, with one crew working to one plan.
Some lifts need engineered lift points or a sealed plan. That work goes through Engineering, and you hear about it at the quote, not on lift day.






FAQ
Questions we get
What do you need from me to plan a lift?
Four things: the nameplate weight and what is still attached, where the lifting points are, where the crane can stand, and what the ground there is made of. A few photos help.
Can the old rooftop unit come down and the new one go up in one visit?
Yes. Both lifts are planned for the same window, so the crane comes to site once.
Does a crane lift need an engineer?
Not always. Every lift is a critical lift with a written plan. Where a lift needs engineered lift points or a sealed plan: our in-house engineer of record, within their scope.
In short
What you get
A written lift plan, a cleared zone and one signaller on every pick. The crane and its operator are hired for the job; our crew plans, rigs and runs the day.
Who’s in charge, and where it stops
The operator runs the crane and our crew lead runs the lift. Lifts that need professional sign-off go to our in-house engineer of record.
Get one
Tell us what it is and where it has to go. Price and timing come in the quote.
Got a piece that has to fly?
Send us the piece and the site, and we'll plan the lift.