Switchgear, transformers, generators and motor control centres. Licensed electricians make the gear dead and prove it. Then our crew rigs it out upright, hauls it dry and sets it lined up at the bus, the bars that carry the current from one section to the next.
The load
Top-heavy, sometimes full of oil, easy to damage
Switchgear line-ups, dry-type and oil-filled transformers, standby generator sets, motor control centres (MCCs, the cabinets that start and protect a plant's motors), drives and panels.



01 · Weight
High and concentrated
A transformer carries its weight in the core and coil, high in the tank. A switchgear section has its breakers and bus up top. Both want to tip. We rig for the real centre of gravity and keep the piece upright.
02 · Fluids
Oil, fuel, coolant, batteries
Transformer oil is tested, documented and handled by the licensed trade. On a generator, the fuel and coolant are drained or isolated and the starting batteries are disconnected before the lift.
03 · Fragile parts
Bus, insulators, relays
Bushings, insulators, bus joints and relays can fail on a hard set-down. Electrical gear has a way of looking fine right up until someone energizes it. So breakers ship separately where they can, and every piece is wrapped against moisture.



How we move it
Lock out, split, haul upright and set
01 · Isolation
Proven dead and locked
Our crew starts only after a licensed electrician has de-energized the gear, proven it dead and locked it out. That includes any source that could back-feed, which means power arriving from the load side. Our locks go on the points that protect the lift, and we walk the lockout before the first bolt comes out. See Safety.
02 · The lift
Splits, lugs and the route out
Switchgear comes apart at its shipping splits, the joints where the sections were bolted together, and lifts by the manufacturer's lugs under a spreader beam that keeps the slings vertical. Small rooms and single doors are specialty rigging. Heavy transformers are jacked, skidded and rolled out, or lifted by crane from their lugs.
03 · On the road
Upright, dry and tied to the frame
The gear is chained at the base and braced at the top so it cannot rock. It is wrapped or crated against rain and road salt and rides on our own trucks. Anything stored between sites is kept indoors in warehousing.
04 · The set
Level and lined up at the bus
The gear is set section by section, shimmed level and pulled into line so the bus joints and frame bolts meet without force. The electricians are licensed sub-trades that we hire and manage as general contractor, under your permits. They land the cables, torque the bus and test, and we stay through start-up. That is installation.
Where it fits
Energy sites, plants and buildings
Electrical gear moves in every sector we serve. The heaviest of it sits on energy sites, and industrial and commercial buildings carry the MCCs, distribution gear and standby power. Gear coming out for sale runs through equipment and plant removal, tagged under Traceability and offered for its owner through equipment sales. If you bought the gear at a sale and need it out, see auction rig-outs.
FAQ
Questions we get
Do your riggers disconnect the cables?
No. Disconnecting and landing cables is electrical work, and licensed electricians do it. Our riggers rig, move and set. We hire and manage the electricians as part of the job, under your permits.
What has to happen before you touch the switchgear?
A licensed electrician de-energizes it, tests it dead and locks it out. That covers the upstream feed, any generator or UPS (battery backup) that could back-feed, and the control power.
Does a switchgear line-up move in one piece?
No. Each shipping split is unbolted at the bus and the frame and moved on its own. Breakers are racked out and shipped separately where they can be.
Does an oil-filled transformer travel full or drained?
Either, as the manufacturer and the receiving site require. The oil is tested, documented and handled by the licensed trade. Large units ship drained under a dry-gas blanket, which keeps moisture out of the tank, with an impact recorder on board to log any knocks.
The electrical room is upstairs with one door. Can you get the gear out?
That is specialty rigging: hydraulic skates, a gantry over the line-up, stair-climbers for small cabinets, and a crane through a wall or roof opening for pieces that will not fit the stairs.