WHAT WE MOVE · ESCALATORS & ELEVATORS

Escalators and elevators

Escalator trusses, elevator machines, cabs, counterweights and rails. The trade belongs to the licensed elevator contractor. The rigging is ours: the pick into the building, the move across the floor and the set. Each job is looked at on its own and planned with the equipment maker, the owner and the licensed elevator contractor.

The load

Long, heavy, and one opening to get through

These pieces have to pass through a finished building and land on their supports exactly where the drawings say.

01 · Escalator trusses

Stiff one way only

A truss is a welded frame as long as the rise it climbs. Lift it from the wrong points and it twists. So we rig from the manufacturer's lift points with a long spreader beam, which holds the slings apart, and we tail the low end, steering it on its own line, so the truss comes in at the angle the opening needs.

02 · Elevator equipment

Machines, cabs, counterweights, rails

A traction machine is compact and dense, and it often goes in through a roof opening. A cab is rigged by its sling, the frame that carries it, and never by its panels. Counterweight fill, the steel plates that weigh down the counterweight, moves as counted stacks. Rails are banded and staged where the elevator mechanic wants them.

03 · The building

The opening is the whole plan

It may be a removed curtain-wall panel, a roof hatch, an atrium or a loading dock. The owner's contractor and engineer size it and shore it. The floor loading under outriggers, the legs a crane stands on, or under gantry legs is confirmed with them before anything is set down.

A picker truck's boom holds a large wrapped tank inside a shop bay, seen from a second angle.
A heavy black steel support frame stands in an empty, cleared bay of a bright industrial building with white wall panels.
A long, symmetrical room with overhead ducting and stacked metal racking along both sides of a polished floor.

How we move it

Plan with the mechanic, pick, walk it in and set

01 · Who does what

Their trade, our rigging

When we run the job, we schedule the licensed elevator contractor alongside the other trades. They hold the elevating-device permits. They align, wire and commission the equipment, and they direct any rigging inside the hoistway, the shaft the elevator runs in. By law, only they install or adjust it. We plan the lift with them.

02 · The pick

Crane or gantry at the opening

A crane lift is worked out on paper first: where the crane sits, the radius, the ground under the outriggers and the path past the facade. On the day there is one signaller, an exclusion zone below, and protection on the edges of the opening. Where no crane can reach, a gantry, a frame that lifts from above, does the lift.

03 · The set

Landed, rolled in and jacked down

The piece lands on rollers or skates, the low carriers that let it roll, and walks across the floor. Jacks and cribbing, which is stacked blocking, lower it onto its supports a little at a time. Where there is no opening at all, it travels in sections through the freight route, under specialty rigging.

04 · Removal and transport

Out in reverse

Old equipment leaves whole, or it is cut into sections under a hot-work plan, the written permit for torch cutting, as equipment removal. Trusses ride on our own trucks, blocked and chained at the frame. Machines and controllers are crated, and anything that arrives early waits indoors in warehousing.

A picker truck with its knuckle-boom crane raised, full-length side view.
A white picker truck with its crane folded beside a long metal-clad building.
A push-around scissor lift staged clean on an empty shop floor, ready for sale.
A yellow mobile crane raising its boom beside a long industrial building in a snowy yard.

Where it fits

Malls, transit, offices and plants

Most escalators and elevators are in commercial buildings: shopping centres, transit stations, airports, office towers, hospitals and hotels. In a plant it is the freight elevators and material lifts, and the work is often part of a larger plant upgrade. Where a building is being cleared, the equipment comes out under deconstruction.

FAQ

Questions we get

Do you install escalators and elevators?

No. The licensed elevator contractor installs the equipment, commissions it and signs it off. We rig it into and out of the building and set it on its supports for them.

Who do you work for, the owner or the elevator contractor?

Either. We can work under the elevator contractor as their rigging crew, or directly for the owner or the general contractor.

Can a truss come in if the building is already closed in?

Often, yes. We assess the building on the site walk. The ways in are a removed curtain-wall panel, a roof opening, an atrium or a loading dock. Failing those, it comes in sections through the freight route.

Do you cut up the old truss or take it out whole?

Whichever the opening and the finishes allow. We make that call with you on the site walk.

What do you need from us to quote?

The equipment drawings, or the manufacturer's weights and lift points. The building drawings around the opening. And the elevator contractor's dates.

Got a truss and one way in?

Send the drawings, the opening and the elevator contractor's dates to sales@rigout.ca, and we will plan the pick with you.