RIGGING & MOVING · MACHINERY MOVING
Machinery moving
One machine or a full shop, moved in, across the floor or out. One crew runs it from the first disconnect to the last anchor torqued, and brings its own lift trucks and trucks to do it.
The sequence
Disconnect, move, set, level, reconnect
A bigger piece makes each step take longer. It doesn't change the order.



01 · Disconnect
Freed, tagged, photographed
Locking out the power and isolating the gas is licensed work. It is done by licensed sub-trades that we hire and manage as general contractor, under your permits. Our crew caps the air, coolant and hydraulics. Every line, cable and bolt that comes off gets a tag and a photo.
02 · Move
Off the pad and across the floor
The machine is lifted on forks, under a boom or on skates, the low rollers it rides across the floor. It travels a path that was measured before the day. Our lift trucks do most of this. The awkward pieces become specialty rigging.
03 · Set, level, reconnect
Landed where it will run
The machine is set to the layout marks, levelled to the maker's tolerance and anchored. Lines go back on in the order they came off, which is what the tags and photos are for. The same licensed trades reconnect the power and services.
Three kinds of move
In, across, or out
New-machine delivery and set
We check the machine for damage while it is still on the trailer, and note it before anything is unloaded. Then we uncrate it, lift it by the maker's points and set it on the pad. Levelling and anchoring follow the maker's sheet.
In-plant relocation
A layout change, or a new cell in a shop that is still running. The move is planned around your production: which shift, which aisle, which machines go dark and for how long.
Move out
A machine sold, traded or headed to another site. The crew that disconnects it also loads and secures it. Then they haul it on our own trucks or load the buyer's carrier, with condition photos either way. Bought a machine at auction, or from a sale somewhere else? We rig it out, crate it and manage the riggers and carriers that bring it to you. For a whole shop, see site and plant moves.
Planning
The walk before the move
For one straightforward machine, a photo and the nameplate are enough. For anything more, we walk the site first and settle three things.
Weight and balance
We start with the nameplate or the maker's data. Then we look at what has been bolted on since: tool changers, chip conveyors, bar feeders.
The path
Door heights and widths, aisle turns, overhead services, pits, trenches and the slab itself. The path decides the method and the gear, so it gets measured, not eyeballed.
The pad
Is the foundation cured? Are the anchors in? Are the services roughed in at the right spot? A machine that arrives early goes into storage, not onto a floor where it is in the way.
What can go wrong
Three risks we plan against
Lifted from the wrong point
Guarding is sheet metal, and a machine lifted by it is bent before it leaves the floor. We lift by the maker's points. Where there are none, we choose points on the frame and check them against the weight.
Shock and tipping in transit
Each load is blocked, chained and padded to suit the piece. Ways, spindles and ball screws are protected. Tall machines ride a lowboy, a trailer with a deck close to the road, to keep them low. See crating and shrink wrap.
Set wrong
A machine out of level walks, chatters and wears, and it tends to wait until the movers have gone home to start. We level to the maker's tolerance and check it again after the anchors are torqued. You see the level before we leave.
See safety for how every lift is run.

What we move
The shop floor, end to end
CNC machining centres, lathes, mills and grinders. Press brakes, shears, plate rolls and other fabrication equipment. Compressors, dust collectors and chillers. Switchgear and electrical rooms. Racking, benches and tool cribs too. When a piece is more than a lift truck can take, it goes to a crane.
One crew, the whole way
One record, start to finish
We keep the job together and keep a single record of it. What the crew learns taking the machine off its pad is still there when it is set down on the next one. Where the move ends with a new foundation and start-up, it runs into installation.



FAQ
Questions we get
Who disconnects the power and services?
Licensed electricians and gas fitters lock out the power and isolate the gas. Our crew caps the air, coolant and hydraulics, and tags and photographs everything that comes off.
What if the new pad is not ready when the machine arrives?
The machine goes into storage at our yard until the pad is ready. The site walk checks the pad before the move, so the plan allows for it.
Got a machine to move in, across or out?
Send a photo and the nameplate to sales@rigout.ca, and tell us where the machine has to end up.
Email sales@rigout.ca.