A long service corridor lined with electrical panels and equipment cabinets.A row of freestanding electrical switchgear cabinets and a dry-type transformer stand on pallets inside a room still framed in unfinished sheathing board.A row of large air-handling units and ductwork lines a mechanical room corridor.

WHAT WE MOVE · DATA CENTRES

Data centres

Racks, UPS and battery strings, switchgear, gensets and cooling units. We assess each move on its own, then run it with you, the equipment maker and licensed specialist contractors where the work calls for them, in phases that fit inside your change windows.

The load

Heavy, live, and no friend of static or dust

Racks and cabinets, UPS modules and batteries, power distribution, standby gensets, and the CRAC and CRAH units that cool the hall. And under all of it, the raised floor, which gets a say in every step.

01 · A live site

Your hall, your rules

We work to your access control, your escorts and your approved change windows, and to a written method of procedure: the step-by-step plan your facilities and IT people sign before anything moves. Aisle containment, the panels that keep hot and cold air apart, stays closed. We do not cut or drill in the hall. And when the site does not match the procedure, our crew stops.

02 · The floor

What the tiles will carry

A loaded rack on castors can put more on one wheel than a tile is rated for. So we get the floor rating first and plan to it: plate or plywood to spread the load, wide skates (the low rollers that slide in under a load), and routes that follow the pedestal grid, the supports that hold the tiles up. The slab, the freight lift and the dock get the same check.

03 · Static, dust and cold

The damage you can't see

Where boards are exposed, the crew works grounded and loose parts go into anti-static bags. Racks are wrapped to keep the dust out. Gear that rode a trailer through a Prairie winter stays sealed until it has come up to room temperature.

A dense equipment rack with junction boxes and labelled control conduits, every circuit tagged before anything is disconnected.
A clean white panelled wall with hazard-striped yellow and black conduit drops and wall boxes above an empty floor.
A bank of white plastic pipe runs racked on strut below a metal-deck ceiling, turning down towards a mechanical wall.
A long, bright room seen from one end with a gridded floor of low trays and tidy overhead ducting and pipework.
A long, symmetrical room with overhead ducting and stacked metal racking along both sides of a polished floor.
A heavy black steel support frame stands in an empty, cleared bay of a bright industrial building with white wall panels.

How we move it

One row, one system, one window at a time

01 · Racks

Servers in, or servers out

A populated rack moves with its servers in place only where you and the equipment maker both allow it, and then it goes braced and strapped. Otherwise the servers come out. Each one is labelled by rack and U position, its slot in the rack, and packed in a foam-lined case so it goes back where it came from.

02 · UPS and batteries

Top-heavy and still holding a charge

The licensed electrician goes first: the UPS is isolated and discharged, the battery strings are disconnected, and every terminal gets a cover. Then the modules ride upright, strapped at the frame. Lead-acid batteries that are not making the trip go to a licensed recycler. Lithium-ion travels under the dangerous goods rules.

03 · Power and cooling

The plant around the hall

Switchgear and transformers follow our electrical method. Gensets come off the pad with the fuel drained or isolated. CRAC units have their refrigerant recovered by a licensed technician first, the same as chillers and refrigeration. All of it travels upright and dry.

04 · The phases

Sequenced around uptime

New racks are set, levelled and powered before the old ones come out. The sequence leaves the last UPS, CRAC or feed where it is for as long as the hall still needs it. Work runs in your change windows, nights and weekends where that is what it takes, and we hand the hall back under its normal rules before each window closes.

Where it fits

Moves, upgrades and closures

Data centre equipment lives in commercial buildings: colocation halls, server rooms, telecom and office buildings. It then runs one of three ways: as a site move, as a plant upgrade where new gear replaces old, or as decommissioning. Where a site is closing, data destruction stays with you. We handle the hardware and record the serials under Traceability. Gensets and rooftop cooling go by crane, and if the new site is not ready, the gear waits indoors in warehousing.

An empty finished room with double doors, windows and a polished concrete floor, cleared and ready for its next use.
Rows of large insulated pipe runs and ductwork along the wall and ceiling of an industrial plant room.

FAQ

Questions we get

Can you move equipment while the data centre is running?

Where the assessment shows it can be done safely, yes. The work follows a written method of procedure that you approve. It runs inside your change windows, one row or system at a time, in an order that protects the hall's redundancy.

Who disconnects and reconnects the electrical gear?

Licensed electricians. They isolate, discharge and lock out the equipment before we touch it. At the new site we are the general contractor on the install: we set the equipment and manage the licensed electricians who land the cables, under your permits.

Will the raised floor take the load?

We start with the floor's rating. Then we spread the load with plate or plywood and run along the pedestal grid. Any span that will not carry the piece gets shored, or the piece is lifted over it.

Do racks move with the servers in them?

Only where you and the equipment maker allow it, and then braced and strapped. Otherwise the servers are de-racked, labelled, bagged against static and packed in foam-lined cases.

What do you need to quote a data centre move?

The equipment list, the hall and dock layouts at both ends, the raised-floor rating, the change windows, and who holds the electrical and fire-protection scopes.

Moving gear in a live hall?

Send the equipment list, the floor rating and your change windows to sales@rigout.ca, and we will start with the assessment.